[All] TransMountain is cancelled
Lanteigne
water.lulu at yahoo.ca
Thu Dec 17 01:25:22 EST 2020
Hi folks
Trans Mountain pipeline contract is 'terminated'.
Macro Spiecapag Trans Mountain Joint Venture, its 50/50 joint venture with Spiecapag Canada Corp., has received a notice of termination from Trans Mountain Pipeline L.P. to “terminate for cause” the construction contract for Spread 5B of the Trans Mountain expansion pipeline project due to ongoing challenges between the joint venture and Trans Mountain.
Trans Mountain pipeline contract 'terminated'
|
|
|
| | |
|
|
|
| |
Trans Mountain pipeline contract 'terminated'
Macro Enterprises Inc. reported Wednesday that Macro Spiecapag Trans Mountain Joint Venture, its 50/50 joint ven...
|
|
|
Earlier today, Canada Energy Regulator says a contractor was seriously injured Tuesday at a Trans Mountain construction site in British Columbia. The injury at the site in Burnaby was reported to the Canada Energy Regulator late Tuesday and its safety specialists were on site Wednesday.Specialists will oversee the company's investigation and conduct an assessment of risk and potential non-compliance.
https://www.cbc.ca/news/canada/british-columbia/contractor-seriously-injured-at-trans-mountain-site-in-burnaby-1.5844931
Construction at Trans Mountain site in Burnaby halted after contractor seriously injured | CBC News
|
|
|
| | |
|
|
|
| |
Construction at Trans Mountain site in Burnaby halted after contractor s...
The Canada Energy Regulator says a contractor was seriously injured Tuesday at a Trans Mountain construction sit...
|
|
|
I don't know if the two incidents are related but it is interesting timing.
Louisette
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://gren.ca/pipermail/all_gren.ca/attachments/20201217/38c7d279/attachment.html>
More information about the All
mailing list